The Effect of Competition on Bid Quality and Final Results on State DOT Projects.
紀錄類型:
書目-電子資源 : Monograph/item
正題名/作者:
The Effect of Competition on Bid Quality and Final Results on State DOT Projects./
作者:
Delaney, Joseph W.
出版者:
Ann Arbor : ProQuest Dissertations & Theses, : 2018,
面頁冊數:
170 p.
附註:
Source: Dissertation Abstracts International, Volume: 79-08(E), Section: A.
Contained By:
Dissertation Abstracts International79-08A(E).
標題:
Transportation. -
電子資源:
http://pqdd.sinica.edu.tw/twdaoapp/servlet/advanced?query=10688753
ISBN:
9780355679168
The Effect of Competition on Bid Quality and Final Results on State DOT Projects.
Delaney, Joseph W.
The Effect of Competition on Bid Quality and Final Results on State DOT Projects.
- Ann Arbor : ProQuest Dissertations & Theses, 2018 - 170 p.
Source: Dissertation Abstracts International, Volume: 79-08(E), Section: A.
Thesis (Ph.D.)--State University of New York at Buffalo, 2018.
The study's objective was to determine if competition during bidding directly affects the end results for State DOT projects. Competition was measured as the number of bidders per bid, and end results were measured as cost overrun and time delay percentages at project completion. State DOTs use a recursive bidding process, a standard project management practice, and they record and archive results in a similar fashion, all according to FHWA regulations. There is therefore a well-built data set for both bid results and final project outcomes which is made available to the public, on-line, by several State DOTs. By accessing public websites, data from five of those State DOTs was utilized in the study, which contained 2,457 certified bid results and 1,040 project outcomes.
ISBN: 9780355679168Subjects--Topical Terms:
555912
Transportation.
The Effect of Competition on Bid Quality and Final Results on State DOT Projects.
LDR
:02903nmm a2200337 4500
001
2201622
005
20190429091134.5
008
201008s2018 ||||||||||||||||| ||eng d
020
$a
9780355679168
035
$a
(MiAaPQ)AAI10688753
035
$a
(MiAaPQ)buffalo:15518
035
$a
AAI10688753
040
$a
MiAaPQ
$c
MiAaPQ
100
1
$a
Delaney, Joseph W.
$0
(orcid)0000-0002-3217-6241
$3
3428340
245
1 4
$a
The Effect of Competition on Bid Quality and Final Results on State DOT Projects.
260
1
$a
Ann Arbor :
$b
ProQuest Dissertations & Theses,
$c
2018
300
$a
170 p.
500
$a
Source: Dissertation Abstracts International, Volume: 79-08(E), Section: A.
500
$a
Adviser: Satish Mohan.
502
$a
Thesis (Ph.D.)--State University of New York at Buffalo, 2018.
520
$a
The study's objective was to determine if competition during bidding directly affects the end results for State DOT projects. Competition was measured as the number of bidders per bid, and end results were measured as cost overrun and time delay percentages at project completion. State DOTs use a recursive bidding process, a standard project management practice, and they record and archive results in a similar fashion, all according to FHWA regulations. There is therefore a well-built data set for both bid results and final project outcomes which is made available to the public, on-line, by several State DOTs. By accessing public websites, data from five of those State DOTs was utilized in the study, which contained 2,457 certified bid results and 1,040 project outcomes.
520
$a
Two statistical models were developed using Multinomial Logit Regression (MLR) and Three Stage Least Squares Regression (3SLS) techniques. The MLR model was developed to provide estimates of the relative importance of bid-phase competition in predicting bid quality. The results showed that the likelihood of achieving an acceptable, versus an unfavorable bid result, was increased by 4.9x with each additional bidder per bid. The 3SLS model was developed to assess the influence of bid phase competition on project cost overruns and time delays. The results showed that each additional bidder per bid resulted in a 2.2 percent reduction in project cost overruns.
520
$a
Both results are significant, as the models showed that as competition increases, the probability of high quality bids and better project outcomes is enhanced. Based on these results, it is recommended that State DOTs consider the existing competitive environment before implementing alternative project delivery methods like Design-Build, or procurement strategies such as Project Labor Agreements, which artificially limit competition.
590
$a
School code: 0656.
650
4
$a
Transportation.
$3
555912
650
4
$a
Management.
$3
516664
650
4
$a
Economic theory.
$3
1556984
690
$a
0709
690
$a
0454
690
$a
0511
710
2
$a
State University of New York at Buffalo.
$b
Civil, Structural and Environmental Engineering.
$3
1023703
773
0
$t
Dissertation Abstracts International
$g
79-08A(E).
790
$a
0656
791
$a
Ph.D.
792
$a
2018
793
$a
English
856
4 0
$u
http://pqdd.sinica.edu.tw/twdaoapp/servlet/advanced?query=10688753
筆 0 讀者評論
館藏地:
全部
電子資源
出版年:
卷號:
館藏
1 筆 • 頁數 1 •
1
條碼號
典藏地名稱
館藏流通類別
資料類型
索書號
使用類型
借閱狀態
預約狀態
備註欄
附件
W9378171
電子資源
11.線上閱覽_V
電子書
EB
一般使用(Normal)
在架
0
1 筆 • 頁數 1 •
1
多媒體
評論
新增評論
分享你的心得
Export
取書館
處理中
...
變更密碼
登入